Topic
The Plan Commission & Architectural Review Board facilities plan, by the numbers.
Figures below are transcribed verbatim from the public records of the 2024-2025 Long-Range Facilities Master Plan, or counted from those tables. Each transcribed figure links to the exact passage it was read from.
The Long-Range Facilities Master Plan is the district's 10+ years facility-condition assessment, prepared by Paragon Architecture. It identifies $94,136,875 Source #q9c0b1057 of needs, broken out by assessment scope and by location Source #q314adaf6 and sorted into three priority tiers, and presents future-development options as a separate frame.
Soft costs (design fees, contingency, construction management, testing, permitting) are not included; the plan recommends adding 10-25%. Source #q0e4a79a2
- May 2024Kickoff meeting and Board of Education introduction Source #q91e78328
- Summer 2024District-wide building assessments Source #q91e78328
- Aug 2024 - Jan 2025Steering Committee and building-level Sub-Committee meetings Source #qebe05cb1
- Nov 13, 2024Volume II (Demographic Study) delivered to the district Source #q65169e11
- Dec 4, 2024 - Jan 22, 2025Board of Education retreats on options, costs, and funding Source #q7ec763b6
- Feb 19, 2025Volume I (the master plan) delivered to the district Source #qae166457
- Jan 21, 2026Board adopts the resolution calling the $135M bond election Source #qf35ce6bf
- April 7, 2026Voters approve Proposition O (2,516 to 303) Source #qe9623191
| Tier | Horizon | Total |
|---|---|---|
| Red | Immediate (2-5 years) | $23,458,924 |
| Yellow | Near-term (5-10 years) | $28,305,058 |
| Green | Long-term | $42,372,894 |
| Priority total | $94,136,875 |
| Scope | Immediate | Near-term | Long-term |
|---|---|---|---|
HVAC $18,786,495 $4,258,800 $12,051,000Immediate (Red)$18,786,495
Near-term (Yellow)$4,258,800
Long-term (Green)$12,051,000
From #q314adaf6
| |||
Building Envelope $1,601,498 $12,358,797 $760,449 | |||
Roofing $1,270,070 $5,409,444 $6,094,320 | |||
Playgrounds & Playfields $403,166 $1,084,965 $1,580,511 | |||
Flooring $208,922 $675,661 $8,765,007 | |||
Ceilings $305,685 $1,346,213 $3,674,371 | |||
Walls $332,522 $1,995,749 $8,009,258 | |||
Parking Lots & Drives $132,944 $891,197 $1,437,977 | |||
Exterior Lighting $417,622 $284,232 $0 | |||
| Location | Immediate | Near-term | Long-term |
|---|---|---|---|
Clayton High School $7,614,544 $13,238,170 $15,623,709Immediate (Red)$7,614,544
Near-term (Yellow)$13,238,170
Long-term (Green)$15,623,709
From #q314adaf6
| |||
Wydown Middle School $1,129,401 $3,283,716 $13,210,122 | |||
Captain Elementary School $3,216,077 $4,222,330 $1,967,932 | |||
Glenridge Elementary School $3,133,871 $2,289,230 $3,221,942 | |||
Meramec Elementary School $4,522,796 $2,483,300 $4,734,302 | |||
Athletics & Activities $986,821 $647,649 $865,139 | |||
The Family Center $2,104,975 $533,347 $1,484,305 | |||
Administrative Center $558,735 $1,167,919 $1,160,071 | |||
Facility Services $191,704 $439,397 $105,372 | |||
These are conceptual options presented on top of the identified-need assessment above — a separate, larger cost frame, not part of the $94,136,875 priority total. Figures are the plan's rounded 2025 estimates and require further study.
| Site | Renovate (Level 2) | Renovate (Level 3) |
|---|---|---|
| The Family Center | $8M | — |
| Captain Elementary | $19M | — |
| Glenridge Elementary | $27M | $44M |
| Meramec Elementary | $27M | $44M |
| Wydown Middle School | $4M | — |
| Clayton High School | $29M | — |
| Athletics & Activities | $23M | $30M |
| Total renovation construction | $137M to $178M | |
As an alternative, the plan prices three new elementary schools at $43M each (New Captain Elementary, New Glenridge Elementary, New Meramec Elementary), totalling $129M.
- Current debt$34,752,000, fully paid off by March 1, 2029 Source #q052c8f51
- Current debt levy$0.5110 per $100 assessed valuation Source #q052c8f51
- Bonding capacity (Feb 2025 projection)Up to $90M of bonds Source #qff7a0c4f
- Annual capital budget≈$4M per year Source #qff7a0c4f
$135,000,000
- Purposeconstructing facility improvements Resolution #qf35ce6bf
- BallotApril 7, 2026, four-sevenths (57.142857%) majority required Ballot #q983908d7
- Estimated debt-service levy$0.6320 per $100 assessed valuation Ballot #q983908d7
- ResultApproved — 2,516 yes (89.25%) to 303 no; four-sevenths majority required Certified results #qe9623191
- Safety & Security
- Maintenance & HVAC
- Accessibility & Inclusiveness
- Curriculum & Programming