Citation in context

#qa2d40267
minutes 2015-08-11 City meeting records #qa2d40267 Open original ↗

August 11, 2015 — Meeting Minutes

These are the minutes of the City of Clayton Board of Aldermen meeting held August 11, 2015. They record attendance, approval of the July 28, 2015 minutes, consideration and adoption of an ordinance (Bill No. 6510 / Ordinance No. 6380) awarding a FY2015 resurfacing contract to Krupp Construction for the base bid of $1,664,335.10 with a requested contingency of $165,000, and acceptance of the Findings, Conclusions and Determination of the Appeal for a sign permit at 7700 Davis Drive (Central Presbyterian Church). The minutes also note routine reports and brief remarks by aldermen and the mayor and show the meeting adjourned at 7:18 p.m.
Cited passage

08-25-15 BOA Minutes August 11, 2015 Page 1 of 3

THE CITY OF CLAYTON

Board of Aldermen City Hall – 10 N. Bemiston Avenue August 11, 2015 7:00 p.m. Minutes

Mayor Sanger called the meeting to order and requested a roll call. The following individuals were in attendance:

Aldermen: Cynthia Garnholz, Mark Winings, Joanne Boulton, Alex Berger III, Rich Lintz, and Ira Berkowitz. Mayor Sanger City Manager Owens City Attorney O’Keefe

Alderman Boulton moved to approve the July 28, 2015 minutes. Alderman Winings seconded. The motion to approve the minutes passed unanimously on a voice vote. PUBLIC REQUESTS AND PETITIONS

None

AN ORDINANCE TO CONSIDER APPROVING A CONTRACT WITH KRUPP CONSTRUCTION FOR THE FY15 RESURFACING PROJECT

City Manager Owens reported that the Public Works Department is requesting approval of a construction contract for the FY15 Resurfacing Project. In 2014, Horner and Horner & Shifrin, Inc. were hired to complete the design of the project. This project will include the replacement of curb ramps that do not meet ADA requirements, the replacement of substandard curb and gutter, base repair where necessary, and the removal and replacement of two inches of asphalt surface. Bids were opened on July 31, 2015. The City received three bids with Krupp Construction submitting the lowest responsive, responsible base bid in the amount of $1,664,335.10. The final engineer’s estimate for this work was $1,773,129.00, so the bid came in under the final estimate.

The City received three bids with Krupp Construction submitting the lowest responsive, responsible base bid in the amount of $1,664,335.10. The final engineer’s estimate for this work was $1,773,129.00, so the bid came in under the final estimate. Staff is not recommending accepting the alternate bid for base repair as the bid prices were higher than expected and last year no base repair was needed in Claverach Park and only 143 square yards were needed on Wydown Boulevard. The second lowest bid came from Ford Asphalt, at $1,700,000.00, only 2.1% higher than Krupp’s. The Capital Improvement Fund has $5,130,000 ($3,514,050 for this portion of the project) budgeted for this activity in FY 2015

City Staff recommends approval of the construction contract with Krupp Construction for the base bid value of $1,664,335.10. In addition to the contract amount, the City Staff requests authorization to approve change orders in an amount not to exceed $165,000, which is approximately 10% of the project cost. This contingency would be used to cover expenditures to correct unknown site issues that become apparent during the project. Recommendation is to approve the ordinance authorizing a contract with Krupp Construction in the amount of $1,664,335.10, plus a contingency of $165,000 for the FY15 Resurfacing Project.

08-25-15 BOA Minutes August 11, 2015 Page 2 of 3

With regard to the contract, Alderman Berkowitz asked if the contractor is expected to repair work that was done incorrectly after the project is completed (i.e. streets buckle, pot holes, etc.); adding if this should be stipulated in the contract agreement. City Manager Owens stated that the City has elements in place where the City engineers will not approve the construction until after it is thoroughly inspected. He added that the City engineers are literally on the site during the construction process. City Manager Owens also noted that Federal contracts do not allow warranties to be included in the contracts. Alderman Berkowitz referenced the brick print project as an example. In the case of the brick print project the contractor was brought back to make those repairs. Dale Houdeshell commented that the same specifications were used last year on the paving projects.

In response to Alderman Berger’s questions, Dale Houdeshell explained that the southeast and northwest areas of the city are the target areas.

Dale Houdeshell stated that Alderman Berger is correct in the timeline for Maryland Avenue – 2018, 2019 and

Original document

This document is too large to preview here. Open the original ↗.